Solution 1 Example Critical equipment does not arrive on time If critical pieces of equipment do not arrive on time the project will fall behind schedule
Solution Example Critical equipment does not arrive on time If critical pieces of equipment do not arrive on time the
Solution Example Critical equipment does not arrive on time If critical pieces of equipment do
not arrive on time If critical pieces of equipment do not arrive on time the project will fall behind schedule
Solution Example Critical equipment does not arrive on time If critical pieces
of equipment do not arrive on time the project will fall behind schedule
Solution Example Critical equipment does not arrive on time If
Solution Example Critical equipment does
(Solution) 1 Example: Critical equipment does not arrive on time. If critical pieces of equipment do not arrive on time, the project will fall behind schedule.

Category: General
Words: 1050
Amount: $12
Writer:

Paper instructions

1 Example: please remove before completing document. Critical equipment does not arrive on time. If critical pieces of equipment do not arrive on time, the project will fall behind schedule. H H Red Negative 1. Add activities to the WBS to ensure with the manufacturer that the equipment is being built or shipped as required. 2. Have a member of project team go to the manufacturing plant to ensure equipment parts are in progress and on schedule. 3. Add steps to the WBS to ensure the manufacturer ships on time. 4. Add steps to WBS to track the shipment as needed. Parts do not ship on assigned date. If possible, have a backup supplier identified and standing by.

Answer

Get Essay Answer
1,200,000+ Questions
Satisfaction guaranteed